When I edit a symbol, the edit does not show up the project, for exaple, I change a 2' window to a 2'3" window.
When I go back in to recheck the edit it says 2'-3" in the system option but does not update in the plans.
Why?
Posted 28 July 2021 - 03:54 PM
As Richard suggests. UNCHECK and RECHECK product code. Openings typically don't regenerate correctly until you do.
Bear in mind ... Adjustments made at system level ONLY affect projects opened after the adjustments are made. Drawings follow PROJECT OPTIONS, not SYSTEM OPTIONS, So you have do do resets to project for drawings and reset to system for project to initiate changes made at system level.